Total Promises
8
Completed
0
In Progress
8
Not Started / Stalled
0
Completion Rate
0%
Promise Grades
Promises by Status
Campaign Promises (8 of 8)
Infrastructure - Roads & Watermains
Continue positive change in roads and infrastructure; maintain and upgrade watermains.
Progress Update:
Watermain projects completed on Hazeldean Road, Spruce Meadows Drive, Tamara Way, Stonehaven Drive, Bridlewood Drive. Cathodic protection program rolled out to extend watermain lifespan.
Evidence & Sources (1)
Pathway & Sidewalk Renewals
Renew and upgrade pathways and sidewalks throughout Ward 23.
Progress Update:
Hydro Corridor trail between Equestrian Drive and Bridgestone Drive widened and upgraded. Pathways renewed between Castlefrank Rd/Heathcliffe Court and McElroy Drive/Morton Drive.
Evidence & Sources (1)
Parks & Recreation Improvements
Invest in parks and recreational facilities in Kanata South.
Progress Update:
$4.4M secured for Kanata Recreation Centre upgrades including splash pad expansion at Walter Baker Park. Monticello Park development underway. Eva James Community Centre renewal planned.
Evidence & Sources (2)
Transit Service & Long-Range Planning
Ensure transit service remains viable for suburban areas; develop long-range financial plans for transit.
Progress Update:
'New Ways to Bus' network overhaul launched April 2025. O-Train Line 1 performance at 98.8%. However, comprehensive suburban transit improvements not fully achieved; service gaps remain.
Evidence & Sources (2)
Community Safety & Traffic Calming
Enhance community safety through traffic calming, better lighting, and road safety improvements.
Progress Update:
Intersection modifications planned at Bridgestone/Windways Crescent and Romina/Eagleson. Some lighting improvements. Comprehensive traffic calming measures not fully achieved.
Evidence & Sources (1)
Fiscal Accountability & Tax Management
Manage municipal finances responsibly and ensure accountability in tax spending.
Progress Update:
Budget advocacy ongoing but property taxes continue to rise (3.75% increase in 2026). Affordability remains a challenge.
Evidence & Sources (1)
Stage 2 LRT West Extension
Support completion of Stage 2 LRT West extension to serve Kanata.
Progress Update:
Track work substantially complete. Overhead catenary power infrastructure being installed. Public opening still pending - expected late 2025.
Evidence & Sources (1)
Kanata South Transit Improvements
Enhance OC Transpo service frequency and reliability in Kanata South.
Progress Update:
Routes 61 and 63 frequency improvements made. New express service added. However, overall transit reliability and service gaps remain concerns for suburban residents.